Capital Improvement Plan

Capital Improvement Program for 2008-2009: Funding and support for major projects and acquisitions. The plan for 2008-2009 proposes authorization for long-term debt issuance totaling $10,727,000. In addition the Town would appropriate $885,000 in Capital Non-Recurring Expenditure (CNRE) funding (of this sum, $445,000 would be derived from the General Fund and the remainder from CNRE fund surplus). The remaining costs would be covered by $786,000 in state grants and $125,000 from the self-sustaining Westmoor Park fund.

Public Safety and Public Works

  • Communications Infrastructure -- $350,000 CNRE
  • Public Works Rolling Stock -- $655,000 Bonding
  • Radio Communication System -- $150,000 Bonding

Transportation & Circulation

  • Traffic Calming -- $250,000 Bonding
  • Bishop's Corner & Town Center Improvements -- $400,000 Bonding
  • Neighborhood Street Improvements, Street Resurfacing, Sidewalk Replacement -- $2,182,000 Bonding
  • Arterial Street Rehabilitation -- $1,419,000 Bonding
  • Pavement Markings -- $60,000 CNRE
  • Bridge & Culvert Rehabilitation, Guardrails -- $68,000 Bonding
  • Storm Sewers Miscellaneous Construction -- $245,000 Bonding
  • Traffic Signal Enhancement -- $20,000 CNRE

Education

  • Bugbee School Improvements -- $226,000 Bonding & $144,000 State Grants
  • Portable Classrooms -- $310,000 Bonding & $190,000 State Grants
  • Computer Infrastructure -- $225,000 CNRE
  • Furniture & Equipment Replacement, Lockers -- $110,000 CNRE
  • Heating & Ventilation Systems, Asbestos Removal, Roofing & Masonry, Window Replacement -- $1,507,000 Bonding & $193,000 State Grants
  • School Building Improvements, Stage and Auditorium Renovations -- $875,000 Bonding & $259,000 State Grants

Parks & Recreation

  • Outdoor Pool Improvements & Reconstruction -- $330,000 Bonding & $80,000 CNRE
  • Greenway Development -- $500,000 Bonding
  • Kennedy Tennis Courts -- $200,000 Bonding
  • Park/Playscape Improvements -- $40,000 CNRE
  • Elmwood Campus Enhancements -- $100,000 Bonding
  • Westmoor Park Improvements -- $125,000 Westmoor Park Fund

Building Improvements

  • Energy Conservation, Town Building Improvements -- $1,260,000 Bonding
  • Fairview Maintenance Facility -- $50,000 Bonding